Recipe

Plan a small embedded project from a request

Use when: someone describes a device in everyday words and you have to build it and prove it works

Goal: a written plan whose every requirement has a test, and a build order that always leaves a working device

Taught in Engineering a project

  1. 1

    List what the device must do. Give each an id, a number, a method and a pass line, and sort them into MVP, intermediate and advanced.

    Example

    D2 (MVP): buzzer starts 60 s ± 2 s after the door opens; stopwatch from door-open to sound; 5 of 5 trials.

    Why: a requirement without a pass line can't fail, so it can't tell you when you're done.

  2. 2

    Boxes for inputs, firmware parts and outputs. Mark the hardware-free parts.

    Example

    reed switch → debounce → door timer (hardware-free) → buzzer, LED.

    Why: the hardware-free boxes are the ones host tests can prove before any wiring exists.

  3. 3

    Parts with dated cost bands; a wiring table with one column per board. Check every row against the pin rules.

    Example

    Buzzer at 35 mA on an Uno R4 pin: over 8 mA, so it goes through an NPN transistor.

    Why: a pin-current or voltage mistake caught on paper costs nothing; on the bench it can cost a pin.

  4. 4

    Order the milestones so each ends in a demo. Pair every requirement with a host test or a bench check in a traceability table.

    • a requirement has no test — write one, or admit it is a wish.
    • a test matches no requirement — drop it, or add the requirement it was protecting.

    Why: the table is how you know "done" without arguing.

  5. 5

    Write steps a stranger could follow, including one failure. Afterwards compare estimates with results and score the rubric.

    Example

    Step 4: hold the door open; at 60 s the buzzer sounds. Step 5: unplug the reed switch; the LED shows a fault.

    Why: the review turns this project's surprises into the next project's requirements.

Common mistakes

  • Writing "fast", "reliable" or "low power" with no number.
  • Putting a board or a pin into a requirement, so nobody questions it.
  • Building every feature before anything works end to end.
  • Testing only on the bench, so a logic bug takes an hour to find.
  • Quoting one exact price instead of a dated band.