Solve a constrained problem with a log barrier
Use when: you have inequality constraints, a strictly feasible starting point is available, and you want every iterate to stay feasible along the way
Goal: a central path of strictly feasible points converging to the constrained optimum as μ shrinks
Taught in Barrier methods and the central path
Quick recipe
-
1
For each inequality constraint g_i(x)\le0, add -\mu\ln(-g_i(x)) to the objective.
Example
For \min x^2+y^2 s.t. 4-x-y\le0: B(x,y;\mu)=x^2+y^2-\mu\ln(x+y-4).
Why: the log term is finite only where every constraint is strictly satisfied, so it's automatically undefined outside the feasible region.
-
2
Locate any x_0 with g_i(x_0)<0 for every constraint, before running any solver at all.
Why: B isn't even defined outside the feasible region, so there is no fallback if you start on the wrong side.
-
3
Run an unconstrained solver on B(x;\mu_k), warm-started from the previous x(\mu_{k-1}).
Why: the barrier term keeps every step of this solve inside the feasible region automatically.
-
4
Set \mu_{k+1}=\beta\mu_k for a shrink factor \beta\in(0,1) (often around 0.1–0.5), and repeat until \mu_k is small enough.
- \mu_k is still large relative to your tolerance — repeat the previous step.
- \mu_k is small enough — stop; x(\mu_k) is your answer, and it is genuinely feasible.
Why: shrinking μ too aggressively can overshoot past where the warm start is still a good guess, the same stiffness tension as growing ρ too fast in Section 2's recipe.
Common mistakes
- Starting from an infeasible or boundary point, where B isn't even defined.
- Shrinking μ so fast that each new subproblem's minimizer is far from the last one, defeating the warm start.